The proposed bond will fund the construction of a new pump station with a capacity of 6.6 million gallons per day and the replacement of 5.15 miles of the existing 12-inch ductile iron water line with new 24-inch water line. These upgrades replace infrastructure originally constructed in the 1960s.
Key Benefits
Increased Capacity: The new pump station will more than double the current capacity.
Improved Reliability: Replacing the aging 12-inch water line with a 24-inch line is anticipated to reduce the frequency of breaks and maintenance issues.
Future-Proofing: These improvements will support the long-term growth and sustainability of Decatur.
Anticipated Project Timeline
Design Phase: June 2025 – September 2026
Construction Start: October 2026 – December 2028
Completion and Service Start: January 2029
WCWSD is committed to Decatur's water infrastructure.
12-Inch Ductile Iron Water Line
Water Pump Station
Extents of Water Transmission Main Improvements
Water Pump Station